Delivery Plan & Gantt
User-wise allocation till delivery, sprint breakup, and week timeline.
Accordions
Charts (SVG)
Icons
Enhanced images
User-wise task allocation & timeline
12 weeks
Plan assumes 6 sprints × 2 weeks (12 weeks). Adjust owners/tasks as needed.
Gantt chart (weeks)
🏁Sprint goals (2-week sprints)Scope aligned
- Sprint 1 (W1–W2): architecture baseline, threat model, telemetry agent MVP scaffolding.
- Sprint 2 (W3–W4): ingestion API + schema contract + raw store; agent redaction.
- Sprint 3 (W5–W6): session store + sessionisation rules v1; governance workflow drafts.
- Sprint 4 (W7–W8): activity classification model v1; dashboard v1; audit logs/RBAC.
- Sprint 5 (W9–W10): intent inference v1; APIs + drilldown; E2E tests; privacy review.
- Sprint 6 (W11–W12): pilot/UAT, bug fixes, hardening, delivery report & rollout plan.
📌Definition of Done (delivery)Operational
- Agent deployed on approved machines; data captured per scope with privacy controls.
- Deterministic ingestion with schema validation; replay supported end-to-end.
- Sessionisation + intent tagging accuracy baselined; KPIs computed and displayed in dashboards.
- RBAC, audit logs, and consent documentation completed.